Present
Anthony Smith (AS) – HATF (Chair)
Mark Frost (MF) – HATF (Independent Technical Advisor)
Susan James (SJ) – Transport Watchdog (Head of Casework)
Shamal Ratnayaka (SR) – Transport for London (Aviation Strategy Lead)
Matt Haywood (MH) – Network Rail (Lead Strategic Planner)
Keith McNally (KM) – CPT UK (Operations Director)
Peter Bradley (PB) – UK Coach Operators Association (UKCOA) (Managing Director)
Cllr Puja Bedi (PB) – Representative from Local Community Forum (LCF)
Christian Wolmar (CW) – London Cycling Campaign (Trustee)
Peter Fisher (PF) – National Highways (Head of Nationally Significant Infrastructure Projects)
Tanvi Vyas (TV) – Heathrow Access Advisory Group
Paul Millin (PM) – Heathrow Strategic Planning Group (HSPG) (Chair, Transport Subgroup)
Nigel Wicking (NW) – Airline Operators’ Committee (AOC) (Chief Executive)
Tracey Waltho (TWa) – Council for the Independent Scrutiny of Heathrow Airport (CISHA) (Chair)
Martin Gilmour – Department for Transport (Deputy Director, Policy, Heathrow Expansion) (observer)
Jack Harrison – Department for Transport (Head of Surface Access, Heathrow Expansion Directorate) (observer)
Tim Leech (TL) – Heathrow Airport Limited (HAL) (Head of Strategy and Sponsorship, Surface Access)
Andy Watson (AW) – HAL (Long Term Growth – Surface Access Lead)
Simi Kullar (SK) – HAL (Sustainable Travel Manager)
Sarah Turner (ST) – HAL (Sustainable Travel and Policy Lead)
Nik Bowyer (NB) – HAL (Long Term Strategy Lead)
Tim Wells (TWe) – HAL (H8 Strategy Manager)
Apologies
Lindsey Olliver (LO) – Regional Co-ordinating Officer (Unite the Union)
Liz Garlinge (LG) – National Highways (Network Development Director)
Alan Tilly (AT) – Hillingdon Council (Transport Planning and Development Team Manager)
Polyvios Polyviou (PP) – Business LDN (Programme Director, Transport)
Sophie Chapman (SC) – HAL (Surface Access Director)
Live Actions
Action 18
HAL to get more information on where passengers are getting travel information from
Update: To be presented at a future HATF Board in Heathrow update.
Owner: HAL
Date opened: 02/04/2025
Target completion date: November 2025
Action 20
HAL to assess impact of expansion on active travel work
Update: To be presented at a future HATF board in Heathrow update.
Date opened: 02/04/2025
Owner: HAL
Target completion date: November 2025
Action 21
HAL to develop annual LCWIP monitoring report to show progress against each spoke.
Update: To be presented at a Sept HATF Board in Heathrow update.
Date opened: 02/04/2025
Owner: HAL
Target completion date: November 2025
Action 25
HAL: to provide more detail about plan for hitting the target for carbon emissions
Update: To be presented at a future HATF Board in Heathrow update.
Date opened: 02/04/2025
Owner: HAL
Target completion date: November 2025
Action 27
HAL to look into Kiss and Fly users, and how we can move them onto more sustainable models including to parking
Update: To be presented at a future HATF Board in Heathrow update.
Date opened: 11/06/2025
Owner: HAL
Target completion date: November 2025
Action 30
HAL to share access accessibility audit findings
Update: To be presented at November HATF Board.
Date opened: 11/06/2025
Owner: HAL
Target completion date: November 2025
1. Welcome and Introductions
The Chair, Anthony Smith (AS), welcomed attendees to the fourth Board meeting of 2025.
2. Minutes and actions from previous meeting
Action Updates
Tim Leech (TL) provided updates on 2 actions (27 & 31), which are provided within the slides
3. Heathrow update
TL provided a Heathrow business and Surface Access update:
- 8 million passengers used Heathrow in August and it was the most punctual August on record
- Mode share was presented, and TL reminded attendees that this data is our profiler data which differs from the CAA data due to the differing data collection methods and sample. There are ongoing discussions with DfT and CAA about how to ensure the data collection process is as robust as possible.
AS asked Nigel Wicking (NW) if they have seen success from an airline point of view. NW responded British airways has worked well as well as NATS, however, there have been some challenges such as baggage mounting up for a few days. There is still lots to do.
4. H8 Business Plan
Tim Wells (TWe) provided an update on the progression of H8 planning, and how HATF can get involved. See slides for more information:
- With expansion at least a decade away, (and subject to securing planning consent) Heathrow needs to continue investing in a two-runway airport in the meantime to ensure the airport continues to operate at a good level.
- Heathrow submitted its H8 Business Plan to the CAA in July. It set out proposals for a 2-runway airport including aspects of Modernising Heathrow.
- The plan will deliver better resilience, better passenger experience, better use of new and existing capacity and better sustainability whilst ensuring value for the customer with a proposed passenger charge of £33.26
- The outcomes for Surface Access include measures that support the decarbonisation of the transport network, and improved passenger experience when travelling to and from Heathrow
- TWe suggested for HATF input, the best time to make any observations/contributions would be around October – November, so CAA can consider any comments and take them into account going forward
AS queried about whether there was investment planned in rail, and TWe responded that there is no larger rail projects in the H8 Business Plan. Any new rail links would likely be brought forward as part of the Expanding Heathrow programme.
AS asked how 10 million additional passengers will impact on surrounding network, and what assumptions are made in respect to mode share. TWe stated that we are not forecasting there will be an additional 10 million, but are increasing our stated capacity by 10 million. Our forecast is that there will be c.89 mppa by the end of H8 (2031), which is c.5 mppa higher than current demand. For business planning we have assumed that mode share will stay at today’s level as passenger numbers rise, because we will continue to support sustainable travel initiatives but there is no significant enhancement (such as introduction of the Elizabeth line) planned. TL confirmed that the development of future mode share targets is dependent on the Expanding Heathrow programme, and we have not yet set out a separate target for H8 period – the current Surface Access Strategy target of 45% therefore applies at the moment but HAL are open to discussing the appropriate target with HATF Board once there is clarity on the future trajectory.
Susan James (SJ) asked if Heathrow are fully engaging with Transport for London (TfL) on this? More airport passengers means less space for general commuters which may cause issues on some services. TWe responded yes, we continue to engage with TfL on this and other stakeholders regarding future demand. Shamal Ratnayaka (SR) added that a lot of focus of our discussion is Modernising Heathrow and Expanding Heathrow, but there is a world where this does not happen, so we need do need to be alive to surface access impacts of H8 proposals as well as to look at other, quicker, options to grow sustainable mode share, such as better bus and active travel provision
Tracey Waltho (TWa) commented that the Development Consent Order (DCO) could be many years away, so need to keep level of ambition in terms of sustainable transport improvements high for H8. TL responded that we will continue to make significant OPEX investment in the Sustainable Travel Zone, which is set out within H8 business plan.
Christian Wolmar (CW) asked where is the £10 billion being spent, if there are no new mode share targets? TWe responded that about half is being spent in resilience such as baggage, punctuality and maintaining ageing terminal assets, with significant investment in passenger experience, sustainability and increasing capacity. SR stated his concerns that there is no mode share target, but there is an increase in passenger numbers.
NW wanted to understand the trade off and opportunities between various transport options, such as Heathrow Express vs Elizabeth Line vs Piccadilly Line, as well as how this will cater for the increase in passenger numbers. TL responded that we are continuing to invest in sustainable travel, such as improved bus and coach and active travel. There is choice for passengers, with Heathrow Express supporting this. NW followed up with have any calculations been undertaken if we took Heathrow Express offline and provided more Elizabeth Lines trains? TL responded no we have not done this, but have been doing modelling under Expanding Heathrow to understand the best mix of transport initiatives to support mode share growth.
Matt Haywood (MH) noted that there are technical considerations around which train services can operate on which lines – it is not necessarily the case that removing one Heathrow service would lead to increases on other services. TL also noted that the full Heathrow Southern Rail Scheme into Surrey and Hampshire require the Heathrow Express paths to work, so there were some larger strategic issues also at play.
5. Expanding Heathrow
Further information provided within slides.
Scheme overview
TL introduced Expanding Heathrow plans and noted the information shared is not the final plan and what is shared is a broad overview. The programme is not fully mobilised and we will continue to work with HATF to shape our transport plans, if the project goes ahead.
Surface Access Components
The Airport National Policy Statement (ANPS) sets out the basis and targets of the planning application (50% public transport by 2030 and 55% by 2040 for passengers and a 25% colleague vehicle trip reduction by 2030 and 50% by 2040 – note that Heathrow have proposed that these dates should shift given that the project has not progressed as expected when the ANPS was written). TL noted that CAA data has Heathrow at 42% Public Transport, but we are working with CAA and Department for Transport (DfT) to ensure these numbers are robust. The ANPS also sets out the requirement for transport mitigation.
Rail – TL noted that there are currently no promoters of new rail schemes. We are looking at which combination of rail schemes would offer greatest benefits to both the airport and wider UK economy and noted that the biggest cost is tunnelling.
TL noted that local southern rail services to Waterloo would offer most value to the airport, followed by Western Rail, due to larger catchment and population density of potential users, it is currently unserved by direct transport links and has shorter length of tunnelling.
SJ enquired is Heathrow is considering freight to use rail? TL responded that we are looking at freight separately to passenger rail, but looking at Colnbrook railhead to deliver material during construction. Viability of using rail for significant sums of general freight and cargo has been assessed previously and found to be limited.
TWa asked whether a decision on night flights impacts on modelling the various scenarios? Nik Bowyer (NB) responded that the passenger demand forecast includes flight times so the impact would be modelled, but any decision on night flights sits outside of the surface access remit.
Keith McNally (KM) asked what is the split of capacity between terminals. TL and SR responded that it is currently roughly 10% for Terminal 4 and 40% for Terminals 2/3 and 50% for Terminal 5 and noted that Terminal 4 will have reduced percentages following expansion
Bus and Coach – TL noted that there are fewer bus and coach services running to south of the airport currently and those that do usually terminate at Terminal 4 or Hatton Cross. The proposed southern road tunnel will make a more viable offering from the south to directly into the central area. This will be supported by a brand new interchange within the current Central Terminal Area which will double the existing capacity. There will also be a proposed new interchange to the west, near to Terminal 5.
TL noted that HAL wish to work with HATF to build a coach strategy and to ensure the increased capacity will be utilised in the most efficient and effective way as possible.
Paul Millin (PM) stated that Surrey will want to work closely all Bus and Coach aspects, but would especially want to consider the impact of southern road tunnel and car parks
Taxi and PHV: Andy Watson (AW) stated that Private Hire Vehicles currently create the largest number of car trips at Heathrow. Suggested proposals include increased backfilling and remote drop off, utilising the parkways
Freight –a virtual consolidation process has been proposed and an aspect currently being considered is how business as usual freight can be continued into expansion.
Active travel – the southern road tunnel is being explored as an option for new active travel provision. This would also provide a safe and direct route for cyclists through the centre of the proposed airport “loop”. Ongoing work looking at how the existing LCWIP will evolve into airport expansion including the existing projects being delivered through H7 and H8 is underway.
Road user charging: a range of charges will be modelled in the context of a holistic surface access strategy to drive the right switch to public transport.
Car parking – we have now established 2025 baseline for the several differing types of parking, which will support on progressing expansion recommendations for parking. HAL have received the questions from HATF following the June Board meeting and will respond to these in a deep dive next year.
Intelligent mobility – technology touches many aspects such as a travel wallet, integrated ticketing and taxi backfilling. This will be encouraged to support behavioural change.
Colleague travel – 5 policies were established in 2019. We have delivered well in the last 5/6 years to reduce colleague single occupancy vehicle trips by 10%, as was shown by 2024 colleague travel survey.
Highways – AW stated that we are currently in dialogue with National Highways to set up an engagement plan. AW also stated that there is no longer the Smart Motorways programme on the M25 so we will consider the implications of this.
DCO and Modelling Process
NB introduced the Development Consent Order (DCO), with more information provided within the slides. A DCO (as opposed to a normal planning consent) is required as it is a nationally significant infrastructure project. We will need to submit a DCO by February 2028 in order to meet dates set out by the Chancellor.
The Airport National Policy Statement (ANPS) states that the surface access impacts of expansion will need to be modelled, using DfT guidance.
NB noted that there is a lot of uncertainty about the future scenarios that would be applicable to Heathrow given the timescales over which impacts and mode shares need to be assessed. Additional scenarios will be explored as well as a fully TAG compliant model suite, which create more realistic views of the future and understand the impact of intervention. We will agree these with our stakeholders.
CW asked does modelling account for external events that are out of our control. NB responded yes, the modelling does provide a range, but rare events such as Covid are not covered by models as such events will be less likely to occur and the consequences are unpredictable.
NW asked if the modelling includes resilience factors, such as the tunnel incident that occurred recently. NB responded that this is something we could think about but is not a standard part of the process required for the DCO submission, as modelling covers neutral days and default behaviours.
How HATF can Support
It was agreed that it was in all stakeholders’ interest to seek to come to a common agreement on the modelling approach used, ideally as early as possible. MF to discuss HATF role further in next meeting as time elapsed – details on thinking provided in the slide deck.
6. A.O.B.
Martin Gilmour (MG) shared that Government has invited proposals for Expansion, a number of which were submitted at the end of July. Government are currently reviewing these and will provide a response in due course. In addition, we are anticipating a formal announcement of a review process for the Airport National Policy Statement. DfT welcomes HATF comment on the existing draft. MF agreed to circulate some initial thoughts to inform a discussion at the next board meeting in November.